Topic: C1000-132 topic 1 question 62

In which status can a Job Plan be modified to add a new task?

A.
NEW
B.
REVISED
C.
INACTIVE
D.
PNDREV

Re: C1000-132 topic 1 question 62

Correct Answer is D. Verified in Maximo